Liverpool Canal Link

Start date: January 14, 2021

Est. end if know: March 29, 2021

Planned Stoppages

Albert Dock Gate, Liverpool South Docks
Starts At: Salthouse Key Bridge
Ends At: Salthouse Key Bridge

NAVIGATION CLOSURE (8.30am Monday 18 January until 5pm Sunday 28 March 2021)

Please be advised, an emergency closure is required at Albert Dock gate, Liverpool South Docks. During a routine operation of the gate, failure in operation of the gate occurred leaving the gate inoperable and resting on the dock bed.
Whilst plans to carry out repair works to the gate cylinders were already in our schedule, these works have now been brought forward, in addition to the recovery of the gate and the required repair works.