Leeds & Liverpool Canal

by

Start date: January 27, 2022
End date: February 26, 2022
Time: 12:00 am – 12:00 am
Planned Stoppages

Starts At: Culvert 121, Red Rock
Ends At: Bridge 63, Red Rock Bridge
Up Stream Winding Hole: At Bridge 64
Down Stream Winding Hole: At Bridge 63

Update on 21/02/2022:

This stoppage has been completed.  We have successfully managed to complete these works ahead of schedule. 

NAVIGATION CLOSURE (8am Monday 31 January until 4pm Friday 25 February 2022)

The details of this Stoppage have changed.  Our contractors have reviewed these works and the scale of the required Stoppage has been reduced.  Stoppage will now take place from 31/01/2022 – 25/02/2022.  We apologise for any inconvenience that this has caused. 

Original message:

A stoppage is required, a CCTV investigation of interior condition of the culvert 121 identified that some reair works are requied.

The works involved will be relinning of the culvert to prevent further deterioration of existing condition grade. Also, construction of two new manholes on either sides of the culvert, repair of the exisiting wash wall and relining the bed of canal with clay.